In brief
Not automatically. It depends on the municipality, the building and the work. In Montreal, By-law 20-030 governs stormwater management, and the City confirms whether your project needs an authorization. Ask the question before choosing the roof drains and requesting bids.
Replacing the roof of a condominium does not automatically mean you must retain rainwater: it depends on the municipality, the building and the nature of the work. In Montreal, By-law 20-030 governs stormwater management, and the question is settled with the City before the work is ordered.
Why does the question come up when the roof is replaced?
On a flat roof, rainwater is carried by roof drains to the building’s piping, then to the sewer. During a replacement, the membrane and the roof drains are often changed. That is when the municipality may look at the flow the building discharges, and it is also the simplest time to install controlled-flow roof drains.
Discovering the requirement once the drains are ordered, or the job has started, costs time. Better to ask at the beginning.
What does By-law 20-030 provide in Montreal?
Montreal’s by-law on connections to the public water and sewer networks and on stormwater management (By-law 20-030) governs how a building manages its rainwater. According to the City of Montreal, an authorization must be requested notably when, after the work, the lot has more than 1,000 m² of impervious surfaces. Under the by-law, any surface other than lawn or vegetation counts as impervious.
Is a roof replacement covered on its own? It depends on the nature of the work: have the City confirm it at the start of the project.
When an authorization is required, the request is reviewed by the water management regulation section (SRGE) of the City’s water department, and controlled-flow roof drains are among the accepted flow control devices. For a specific case, check directly with the City. See also civil plans for permits.
And elsewhere in Quebec?
Each municipality sets its own requirements. Some limit the flow a building can discharge into their network; others ask for nothing for a roof replacement. The only reliable answer is the one from your municipality, for your building and your work.
If retention is required, where does it happen?
It can be done on the roof itself, without taking up any space on the ground. How it works is described on our page about roof target flows and discharge control. This article sticks to what your condo board needs to check and decide.
In what order should you proceed?
For a condo board, taking the steps in the right order avoids backtracking.
- Ask the municipality whether the planned work is covered, before requesting any bid.
- Have the requirement established. If a study is requested, the civil engineer determines what the building must retain and prepares the calculations and the documents to be filed.
- Have the roof checked. The structural engineer confirms that it can carry the retained water.
- Have the roof drains selected. The mechanical engineer selects them and checks the interior plumbing.
- Request the bids. The roofers then price the same roof drains and the same details.
We handle the civil scope and coordinate it with the other parties.
And after the work?
In Montreal, once the system is built, the owner must keep it in good condition and keep a record of its maintenance. For a condominium, that means planning the periodic cleaning and checking of the roof drains and overflows.
Where to start
Before asking for bids, gather:
- the roof plans and the roof area;
- the number and location of the roof drains;
- a description of the planned work;
- any letter or comment from the municipality.
Send us this information: we will tell you what needs to be checked and, where applicable, what the study should include.
Frequently asked questions
-
Who confirms whether an authorization is required?
-
The municipality. In Montreal, authorization requests for stormwater management are reviewed by the water management regulation section (SRGE) of the City’s water department.
-
Will water stay on our roof?
-
Only during a heavy rainfall and shortly after, at a shallow depth set at the design stage. Before any decision, the structural engineer checks that the roof can carry it.
-
Should we wait for the roofers’ bids before looking into it?
-
No, the other way around: it is better to know what is required before asking for bids, so that every roofer prices the same roof drains and the same details.
-
How much does the study cost?
-
It depends on the roof area, the number of roof drains, the documents available and what the municipality requires. Request an estimate: the service proposal sets out the scope and the schedule before we start.