Preconstruction: why check the municipal services before developing a lot?

Sewer depth, capacity, water main, storm discharge point: why check the municipal services before buying a lot or starting design.

In brief

Because the networks decide what is possible. The depth of the sewer sets the building’s grades, the allowable discharge rate determines the retention to plan for, and the water main available governs the service connection. Checking before you buy or design avoids discovering these constraints at the permit stage.

Before developing a lot, you need to check the municipal services because they decide what is possible: the depth of the sewer sets the building’s grades, the allowable discharge rate determines the retention to plan for, and the water main available governs the service connection. Discovering these constraints at the permit stage means going back to the design.

What needs to be checked?

The sanitary sewer. Is there one in front of the lot? How deep is it? Can the lowest floors of the project connect to it by gravity, or will pumping be needed?

The storm sewer, or combined sewer. Where can the project discharge its rainwater, and at what rate? The answer sets the volume to retain on site: on the roof, at the surface or underground.

The water main. Is a main available, and of what diameter? Is the intended water service possible?

The right-of-way and the constraints. Servitudes, existing infrastructure, street grades: everything that limits where you can dig and connect.

See site servicing and municipal connections.

Where do you find the information?

From the municipality first: network plans, connection requirements, stormwater management criteria. Then on site: visible manholes and catch basins give actual elevations, which can be measured.

A feasibility analysis gathers this information and draws conclusions from it. It is neither an official confirmation of capacity nor an authorization: both come from the municipality.

What happens if you don’t check?

The constraints surface later, at the worst time.

  • The building’s grades are set, then it turns out the sewer is too high: you have to pump, or raise the building.
  • The site plan is finalized, then it turns out stormwater has to be retained: room has to be found for a structure nobody planned for.
  • The network does not run in front of the lot: an extension has to be planned.

Each of these discoveries changes the project, its schedule and its budget.

When should you check?

As early as possible: before the purchase, during the due diligence period, or before the first sketches. A first analysis can be done with little data, and it steers everything else.

What does a civil feasibility study contain?

It is modular. Depending on the project, it can include:

  • a review of the project and the documents available;
  • a site study: grades, slopes and existing drainage;
  • the municipal networks and the possible connections;
  • a review of the applicable requirements;
  • a comparison of connection, drainage and retention scenarios;
  • a preliminary budget estimate for the civil works, presented as an order of magnitude, with its assumptions and exclusions;
  • a report, with the risks and the steps to take.

Not every mandate includes all of these steps: you can start with the essentials.

In Montreal: By-law 20-030

In Montreal, connections to the networks and stormwater management are governed by By-law 20-030. Depending on the scale of the project, an authorization from the City may be required before the work begins; the thresholds and the procedure are covered in our article on the by-law. It is a point to check at the feasibility stage.

Where to start

Send us the address or lot number, the intended project and the documents available. See how we work with architects, developers and contractors and our civil plans for permits, then tell us about your lot.

Frequently asked questions

Does the municipality confirm the capacity of its networks?

Only the municipality can confirm it officially. The feasibility study gathers the information available, indicates what to ask the municipality and flags the risks. It is neither a confirmation of capacity nor an authorization.

Is a full topographic survey needed at this stage?

Not always. The data available and a few targeted measurements are often enough for a first analysis. The full survey, coordinated with our partners, comes with the design.

Does the feasibility study include a soil study?

No. Geotechnical and environmental studies are carried out by specialized firms; we coordinate them when needed.

How much does a civil feasibility study cost?

It depends on the size of the lot, the intended project, the data available and the steps selected. Request an estimate: the service proposal sets out the scope and the schedule before we start.