Decide in this order: grades and drainage, pavement structure, then the surfacing for each zone. Asphalt suits aisles and stalls, concrete suits heavy loads, pavers suit pedestrian areas. Sidewalks, curbs, bases and conduits are drawn before paving, not after.

A parking lot is designed from the bottom up: grades and drainage, pavement structure, then the surfacing for each zone. Sidewalks, curbs, concrete bases and conduits are drawn at the same time, because they sit under the surfacing or against it. This article is for developers and contractors preparing a new parking lot or a full reconstruction.

In what order should decisions be made?

The surfacing is the most visible decision, and one of the last to make.

  1. Geometry. Aisles, stalls, entrances, delivery area, pedestrian routes. The number of stalls, their dimensions and the aisle widths are generally set by the municipality’s zoning by-law.
  2. Grades and drainage. Where the water goes, at what slope, to which catch basins, and with what retention if the municipality requires it.
  3. Pavement structure. What is needed under the surfacing to carry the expected vehicles on the soil in place.
  4. Surfacing for each zone. Asphalt, concrete, pavers or permeable pavers.
  5. Concrete works. Sidewalks, curbs, islands.
  6. Bases and conduits. Light poles, EV chargers, bollards, gates.

Reversing that order is costly: a surfacing chosen too early imposes its thicknesses and slopes on everything else. For the water side, see our page on drainage and stormwater management.

Pavement structure: what the surfacing cannot make up for

A parking lot is a stack of layers: the soil in place, a granular sub-base and base, then the surfacing. The granular layers spread the loads and drain the water; the surfacing protects the whole and provides the running surface. The ruts and cracks that appear after a few winters most often come from below: frost-susceptible soil, a base that is too thin, or a base that stays saturated.

Three inputs set the thicknesses:

  • the soil in place, its bearing capacity and its frost susceptibility;
  • the loads: an aisle used by delivery trucks, collection trucks or emergency vehicles is not built like a row of car stalls;
  • drainage of the base: a base that stays wet freezes, heaves and loses bearing capacity at thaw.

Characterizing the soil and recommending a structure is the role of the geotechnical study. The civil engineer builds those recommendations into the plans, zone by zone. Without a study, thicknesses are chosen out of habit, and the same detail ends up on sand and on clay.

Which surfacing for which zone?

No surfacing suits an entire site. The “initial cost” column gives a relative order between surfacings, not a price: the actual cost depends on the structure, the quantities and the market.

Surfacing Where it fits Durability Maintenance In winter Relative initial cost Points to watch
Asphalt Drive aisles and stalls Good if the base and drainage are adequate Regular: crack sealing, local repairs, periodic resurfacing Easy to plow Low to medium Marks under heavy stationary loads: trailer landing gear, containers, tight truck turns
Concrete Delivery areas, dumpster pads, entrances, truck turning areas High if the concrete and the joints are well designed Low; repairs are heavier when they occur Needs a mix designed for freeze-thaw and de-icing salts High Joint layout, curing, transitions to asphalt
Concrete pavers Plazas, pedestrian crossings, entrance areas Good; pavers can be replaced one by one Medium: joint refilling, relevelling of settled areas Plow blades need adjusting High Performance tied to the base and the edge restraints; easy access to buried services
Permeable pavers Stalls and low-traffic areas, if the soil and water table allow Good if maintenance keeps up High: periodic joint cleaning to keep infiltration No abrasives, which clog the joints High Reservoir base to be sized; to be validated with the municipality; not suited to every soil

Two remarks on this table. The durability of a surfacing depends first on what lies beneath it: asphalt on a good structure can outlast concrete on a poor one. And the initial cost says nothing about the life-cycle cost, which depends on the maintenance the owner will actually carry out.

Permeable pavers deserve a note. They let water pass through their joints into a base that stores it, then infiltrates it or releases it slowly. They can reduce the volume of the other retention works, if the municipality recognizes them in its calculations. They are not a surfacing laid in place of another: they are a stormwater structure, and they have to be sized.

Sidewalks and curbs: concrete against frost and salt

Sidewalks and curbs are the most exposed works in a parking lot: freezing, thawing, de-icing salts, snowplow blades, wheels riding over them.

Reinforced or not? A sidewalk reserved for pedestrians is generally plain concrete, on a drained granular base. As soon as vehicles cross it, at an entrance, at a delivery access or along the snowplows’ path, it is designed for those loads: a thicker slab, reinforcement, or both. Reinforcement replaces neither the base nor the joints.

Joints. Concrete shrinks as it hardens, then moves with temperature. Control joints decide where it will crack; expansion joints separate it from whatever does not move the same way: building, bases, manholes, curbs. A joint layout is drawn before the pour. Without one, the slab picks its own cracks.

Freeze-thaw and salts. Three precautions go together: air-entrained concrete designed for that exposure, careful curing, and slopes that do not let water sit on the slab. For sidewalks, curbs and exterior slabs in concrete that is not structurally reinforced, exposed to freeze-thaw cycles and de-icing salts, standard CSA A23.1 specifies exposure class C-2. Structurally reinforced works fall under a class set in the specifications.

Curbs. Cast in place or precast, they restrain the pavement and the pavers, guide water to the catch basins and protect the islands. They are lowered at pedestrian crossings and in front of accessible stalls. Their layout is checked against the turning radii of trucks and snowplows: a curb that is too tight is a curb broken in its first winter.

Concrete bases: light poles, chargers and bollards

Light poles, EV chargers, bollards, gates: each sits on a concrete base, and almost all are linked by buried conduits. They are small works, but they are decided early, because they sit under the surfacing.

The civil plan sets:

  • the location of each base, out of the path of vehicles and snowplows, in an island or behind a curb where possible;
  • the grade of the top of the base relative to the finished surface;
  • the conduits: their route, their crossings with the storm pipes, and the empty conduits laid in advance for future chargers;
  • the drainage around the base, so that none ends up in a low point.

The structural design of the base belongs to a structural engineer. The lighting study and the electrical design belong to specialized professionals. The civil engineer works from their plans and coordinates the whole. For a charging project, see our page on civil engineering for EV charging.

Example: a commercial parking lot of about 90 stalls (fictional case)

A new retail store, about 90 stalls, a delivery area at the back and a sidewalk along the storefront. Here is how the decisions follow one another.

  1. Grades and drainage. The slopes carry water to catch basins placed in the aisles, away from the store entrance. The retention required by the municipality is handled with the drainage.
  2. Structure. The geotechnical study reports frost-susceptible soil. The aisle used by trucks gets a reinforced structure; the rows of stalls, a standard one.
  3. Surfacing. Asphalt for aisles and stalls. A concrete slab for the delivery area and the dumpster pad. Concrete pavers on the entrance plaza.
  4. Concrete. Storefront sidewalk in plain concrete, except at the truck access. Lowered curb in front of the accessible stalls. Joint layout on the plans.
  5. Bases and conduits. Light poles in the islands. Empty conduits laid to two rows of stalls, for future EV chargers.
  6. Winter. A snow storage area at the back of the lot, downstream of the pedestrian routes and near a catch basin.

The developer then goes to tender with plans on which each zone has its structure and its surfacing. Contractors bid on the same quantities.

Eight common mistakes

  1. Choosing the surfacing before the slopes and drainage are settled. New surfacing keeps the puddles the slopes give it.
  2. Using the same structure across the whole site. The truck aisle deforms, or the rows of stalls are overbuilt.
  3. Doing without a geotechnical study. The thicknesses are then a guess.
  4. Pouring concrete without a joint layout. Cracks appear where nobody wanted them.
  5. Forgetting the bases and conduits. New surfacing gets saw-cut to run a conduit.
  6. Planning nothing for snow. It ends up piled on stalls, and meltwater refreezes on the sidewalks.
  7. Putting the entrance or the accessible stalls at the low point. That is where water collects and ice forms.
  8. Laying permeable pavers without a maintenance plan. Clogged joints no longer infiltrate anything.

Who designs what?

  • The civil engineer: grades, drainage, pavement structure from the geotechnical study, surfacing, sidewalks, curbs, plans and specifications.
  • The geotechnical firm: soil characterization and structure recommendations.
  • The structural engineer: bases, pedestals and structural slabs.
  • Lighting and electrical specialists: the lighting study and the electrical design.
  • The contractor: construction, its means and methods, and site safety.

Our page Parking lots, paving & civil site works describes what we take on and how a mandate unfolds. Is your project a condominium rehabilitation? Read Rehabilitating a condominium parking lot: where do you start? instead.

Frequently asked questions

Asphalt or concrete for a commercial parking lot?

Both, most of the time. Asphalt suits aisles and stalls; concrete suits areas where loads are heavy, concentrated or stationary: delivery area, dumpster pad, entrances. The choice is made zone by zone, according to the loads, the planned maintenance and the budget.

Do permeable pavers work in a Quebec winter?

They can, under certain conditions: suitable soil and water table, a properly sized reservoir base, regular joint maintenance and snow removal without abrasives. They are validated case by case, with the municipality.

Does a concrete sidewalk need reinforcement?

Not for pedestrian use, as a rule. It does have to be designed for the loads as soon as vehicles cross it: an entrance, a delivery access, the path of the snowplows. Reinforcement replaces neither the base nor the joints.

Who designs light pole bases?

The civil engineer plans their location, their grade, the conduits and the drainage. The structural design of the base belongs to a structural engineer; lighting and electrical work, to specialized professionals.

How much does parking lot design cost?

It depends on the area, the data available, the number of structures to design and how much support you want during construction. Ask for an estimate: the service proposal sets out the scope and the schedule before we start.