Rehabilitating a condominium parking lot: where do you start?

Assessment, slopes, drainage, pavement structure, plans and specifications: the steps to plan a parking lot rehabilitation and compare contractors’ bids.

In brief

Start with an assessment, not with bids: grades, slopes, drainage and the condition of the surfaces. That is what makes it possible to choose between resurfacing and reconstruction, and then to prepare plans and specifications on which every contractor bids on the same basis.

To redo a condominium’s parking lot, start with an assessment, not with bids. It establishes why the lot deteriorated and what really needs redoing; the plans and specifications that follow then give every contractor the same basis for pricing.

Why not ask for bids right away?

Without plans or specifications, each contractor proposes a different solution: one resurfaces, another rebuilds, a third adds catch basins. The prices cannot be compared, because they do not cover the same work. And none of these proposals says why water has been ponding in the same spot for years.

Step 1: the assessment

The engineer visits the lot and measures what matters:

  • grades and slopes;
  • the location and condition of catch basins and manholes;
  • the places where water ponds, ice forms or the surface settles;
  • the condition of the asphalt, the curbs and the sidewalks.

Your own observations are valuable: photographs taken after a rainfall or during a thaw show what a dry-weather visit does not.

Step 2: understand why the lot deteriorated

Three things decide how long a parking lot lasts: the slopes that carry water to the catch basins, the drainage that takes it away, and the pavement structure under the asphalt. When the condition of the base calls for it, borings or a geotechnical study are entrusted to a specialized firm.

Step 3: choose the work

Resurfacing, partial or full reconstruction, drainage corrections: the engineer compares the options, the quantities and their effect on construction costs. The board then chooses knowing the consequences of each option, including that of redoing only part of the lot.

Step 4: plans and specifications

Grading and drainage plans, pavement and curb details, technical specifications and a schedule of quantities describe the work precisely. Every contractor bids on the same documents: the prices become comparable.

Step 5: check the municipal requirements

Rehabilitation work can raise stormwater management requirements, depending on the municipality and the extent of the work. In Montreal, according to the City, an authorization must be requested notably when the lot has more than 1,000 m² of impervious surfaces after the work.

Is the rehabilitation of an existing parking lot covered? It depends on the nature of the work: have the City confirm it.

It is better to check before the design is set: see civil plans for permits.

Step 6: during construction

Depending on the mandate, the engineer makes targeted site visits or carries out partial inspection, and answers the contractor’s technical questions. The work is compared with the plans while there is still time to correct it.

What about indoor or multi-level parking?

Structural slabs, multi-level parking structures and waterproofing membranes belong to a structural engineer or a building envelope specialist. Civil engineering comes in for the grades, the slopes, the flow toward the drains and the stall layout: see, for example, this condominium parking area in Laval.

What to prepare before the first conversation

  • the existing plans of the lot, if any;
  • the history of repairs and maintenance;
  • photographs of the problems observed;
  • the planned timing of the work.

Then tell us about your project. See also our pages on site grading and parking lots and drainage.

Frequently asked questions

Resurfacing or reconstruction: how do you decide?

By the cause of the deterioration. If the base is sound and the slopes work, resurfacing may be enough. If water ponds, the base is failing or the drainage no longer works, a new surface laid on the same defects will fail the same way.

Do you need an engineer to redo a parking lot?

As soon as the work changes the slopes, the drainage or the pavement structure, an engineer’s plans and specifications give the bids a common basis and make it possible to check the work. The municipality may also require plans for certain projects.

How long should we plan for?

The service proposal sets out the steps and the schedule of the engineering mandate, once the file has been reviewed. The construction schedule then depends on the area, the season and the contractor selected.

How much do the plans and specifications cost?

It depends on the area, the condition of the lot, the data available and the level of support wanted during construction. Request an estimate: the service proposal sets out the scope and the schedule before we start.

Terraxis Conseil

Is your condominium preparing to redo its parking lot?

Tell us about the lot, its problems and your timeline: an engineer replies within 48 hours.

Related articles

Talk to an engineer 514-946-4567